Kabalega International Airport in Hoima, the airfield built to serve Uganda's oil fields, is a step closer to becoming a passenger gateway for western Uganda. On 30 October the government, through the Ministry of Works and Transport, signed a Shs232 billion contract (about US$62 million) with Egypt's SAMCO National Construction Company to build a new passenger terminal at the airport, with a completion deadline of eight months.

For travellers and the tourism trade, the deal matters because Kabalega sits in the Albertine region, home to Lake Albert, the Budongo forest and Murchison Falls National Park. Today most visitors to the area drive several hours from Kampala or Entebbe, or use small charter airstrips. A second international airport with a proper terminal would give tour operators a new way to route safaris in the west, and it is being readied for the Africa Cup of Nations (AFCON) 2027, which Uganda co-hosts with Kenya and Tanzania. Hoima is one of the tournament's venues.

What was signed

The contract was signed at the ministry's headquarters in Kampala, the Daily Monitor reported. Fred Byamukama signed for the government, while Egypt's ambassador to Uganda, Sherif Mohamed Abdellattif Elgammal, signed on behalf of the contractor. The Monitor reported that the deal sets a strict eight-month completion timeline.

According to the Daily Express, the airport's existing terminal can handle about 100 passengers at a time. The new building is planned to handle up to 1,000 passengers at peak. The paper reported that Byamukama said SAMCO's price was lower than the Shs285 billion reportedly quoted by China Communications Construction Company and other bidders, a saving of more than Shs50 billion. He urged the contractor to deliver quality work and warned against corruption and interference in the project.

SAMCO's vice chairman, Ibrahim Mabrouk, said the company was ready to start construction and confident of finishing within eight months or sooner, the Daily Express reported. Olive Birungi Lumonya, acting director general of the Uganda Civil Aviation Authority (UCAA), pledged technical support and described the airport as important for travellers, tourists, AFCON visitors and the oil and gas sector. The Monitor reported that UCAA and technical consultants designed the terminal to meet civil aviation security and operational standards.

From oil airfield to passenger airport

Kabalega was first planned under the Ministry of Energy to fly in heavy machinery and equipment for oil development in the Albertine region. Construction began in 2018. The main runway, 3.5 kilometres long, and the cargo set-up are complete, and the government has since moved the facility under the Ministry of Works and Transport and UCAA for commercial passenger traffic.

The airport received its first passenger aircraft on 27 September 2026, when officials from the Confederation of African Football (CAF), FIFA and the AFCON local organising committee flew in as an operational test of the runway, air traffic control and support systems. Uganda Airlines also carried the Uganda Cranes and the Libyan national team to Hoima for an AFCON 2027 qualifier at Hoima City Stadium, according to the Association for African Travel and Tourism (ATTA). Byamukama said at the time that the airport was about 99 per cent complete.

The first phase, which cost about Shs1.2 trillion, is close to finished, and full commercial operations are expected to start in January 2027, according to ATTA and the Daily Express. The new terminal is the airport's second phase. If SAMCO meets its eight-month deadline, the larger building would be ready around mid-2027.

Why it matters for tourism

Uganda's international arrivals are funnelled almost entirely through Entebbe. A working airport in Hoima would give the west of the country its own front door, shortening the trip for visitors heading to the Lake Albert shoreline, the Budongo forest and the southern and western parts of Murchison Falls National Park. It could also help lodges and operators in the Albertine region sell shorter itineraries to travellers with limited time.

The project is also part of Uganda's wider AFCON push. The Uganda Tourism Board has signed on as an official destination sponsor of the 2027 tournament, and the government is betting that football fans can be turned into repeat visitors. See our report on Uganda Tourism Board's AFCON 2027 sponsorship for more on that strategy.

Some questions remain open. Neither the ministry nor UCAA has announced which airlines will fly scheduled services to Kabalega, how often, or from where. The tight eight-month build also leaves little room for delay if the new terminal is to be ready during the tournament.

What it means for travellers

For now, nothing changes for visitors: Entebbe remains Uganda's only scheduled international gateway, and the drive from Kampala is still the standard way into Murchison Falls and the Lake Albert region. Commercial flights into Kabalega are expected from January 2027, initially through the existing small terminal.

Travellers planning a 2027 trip to western Uganda, especially around AFCON, should watch for airline announcements before booking ground transport. For park fees and costs once you arrive, see our guide to Murchison Falls trip costs and park fees.